January 31 Third Floor is added
January 21 Second Floor is added
January 7, 2010, first floor framed in
More Pictures
11/19/2009
The housing progress is moving along - the driveway
and parking lot were covered with plastic
underlayment and stone.
The footers have been poured
and block up to the ground level have been
installed. Insulation was put around the block prior
to back filling.
The entire inside of the
foundation has been filled with stone prior to the
laying of the concrete floor.
Today the plumbers were
starting to install the plumbing fixtures that will
go under the first floor concrete floor. It is
expected that this should be completed early next
week, weather permitting.
Once the plumbing is installed
and inspected by the county code enforcement
officer, the foundation floor will be poured and
work can begin on the outside walls which will be
wood.
The concrete block tower is up
two stories and probably will be finished soon.
The tap for the sewer into the
village main that comes down from main street was
successfully completed. A tap for the water was also
completed, and water lines run down from Cayuga
Street .
11/08/2009
The
Interlaken Senior Housing project is off to a flying
start under the leadership of the construction firm
of Conifer-LeChase.
The
driveway and parking lot off Cayuga Street has been
dug, plastic underlayment and stone placed and
rolled. The drive way is now passable for large
trucks - Asphalt will probably be installed in the
spring.
The
construction trailer is in place behind the storage
sheds off Cayuga Street, (entrance facing east ).
The site is a “Hard Hat” area so please stop at the
trailer prior to entering the site.
The area to
collect runoff has been bulldozed out, and barriers
put in place to prevent the runoff of silt into the
adjacent stream.
The
building area has been leveled and the concrete
poured for the footers. Cement blocks have been
installed up to ground level for the building.